A promoter cannot advertise, book or sell a plot, apartment or building in a real estate project without registering the project with the Real Estate Regulatory Authority. In Tamil Nadu that authority is TNRERA. The registration number must appear in advertisements, and the project page on the Authority's website becomes the public record of approvals, bookings and completion status.
Registration is the first compliance step, not the last. The promoter must keep the project page current, deposit seventy per cent of the amounts realised in a separate scheduled bank account, sell only under a registered agreement for sale, and complete the project within the declared timeline. The Authority can extend the registration in limited circumstances and can revoke it for default or unfair practice.
This guide explains the registration threshold, the documents and the thirty-day decision, the escrow rule, the duties that continue after registration, and the consequences of default. We advise promoters on registration and compliance and represent buyers and promoters in proceedings before TNRERA.
When registration is required
Section 3(1) bars a promoter from advertising, marketing, booking, selling or offering for sale any plot, apartment or building in a real estate project without registering the project with the Authority. The bar applies to a project or any part of it in a planning area.
Section 3(2)(a) exempts a project where the land proposed to be developed does not exceed five hundred square metres or the number of apartments does not exceed eight, inclusive of all phases. The appropriate Government may reduce either threshold. Section 3(2)(b) exempts a project that had a completion certificate before the Act commenced, and Section 3(2)(c) exempts renovation or repair work that does not involve marketing, advertising, selling or a new allotment.
The Explanation to Section 3 treats every phase of a phased project as a stand-alone project. A promoter who registers the first phase cannot rely on that registration for a later phase. Each phase needs its own application, its own declaration and its own completion timeline.
The application and the thirty-day decision
Section 4(1) requires every promoter to apply in the form, manner and time, and with the fee, specified by the Authority's regulations. Section 4(3) requires the Authority to run a web-based system for applications, and TNRERA's portal is the route for filing.
Section 4(2) lists the documents. They include the promoter's enterprise details, the projects launched in the past five years and their status, the approvals and commencement certificate, the sanctioned plan and layout, the development plan and facilities, the land location and boundaries, the proforma allotment letter and agreement for sale, the carpet area and garage details, the agents and contractors, and a declaration supported by an affidavit. The declaration covers legal title, encumbrances, the completion period and the seventy per cent escrow.
Section 5(1) gives the Authority thirty days to grant registration with a registration number, login id and password, or to reject the application for reasons recorded in writing. No application can be rejected without giving the applicant an opportunity to be heard. If the Authority does neither within thirty days, Section 5(2) deems the project registered and requires the registration number and login details to be issued within seven days after that period.
Section 5(3) makes the registration valid for the period the promoter declared for completion of the project or phase under Section 4(2)(l)(C). That declared period is the reference for delay, extension and the buyer's remedies.
The seventy per cent escrow
Section 4(2)(l)(D) requires the promoter to declare, on affidavit, that seventy per cent of the amounts realised from allottees will be deposited in a separate account in a scheduled bank. The money may be used only for the cost of construction and the land cost of that project.
The promoter may withdraw from the account in proportion to the percentage of completion. The first proviso to the clause sets that proportion. The second proviso requires a certificate from an engineer, an architect and a chartered accountant in practice that the withdrawal matches the completion level. The third proviso requires the promoter to have the accounts audited within six months after the end of every financial year and to produce a certified statement showing that the collections were used for the project and that withdrawals stayed within the permitted proportion.
The rule exists because project money is not the promoter's general revenue. In Bikram Chatterji v. Union of India, the Supreme Court froze the bank accounts of forty Amrapali group companies and directed an escrow account after a forensic audit showed diversion of more than rupees two thousand seven hundred crore from six projects. The Court recorded that money paid by buyers for a particular project could not have been diverted to other uses.
Ongoing projects
The first proviso to Section 3(1) required promoters of projects that were ongoing when the Act commenced, and for which no completion certificate had been issued, to apply for registration within three months. The same logic applies to a phase that is still under construction: it needs registration even if an earlier phase was completed.
In Newtech Promoters and Developers Pvt. Ltd. v. State of Uttar Pradesh, the Supreme Court upheld the application of the Act to ongoing projects. The Court described the Act as retroactive in operation and held that promoters of incomplete projects had to register and declare fresh timelines for the remaining work. The decision removed the argument that projects launched before 2016 fell outside the Act.
A promoter registering an ongoing project should reconcile the original approvals, the work completed, the amounts collected and the balance work. The completion period declared in the application should reflect the remaining work, not the original brochure date. The project page and the quarterly updates should then be brought up to date.
Promoter duties after registration
Section 11(1) requires the promoter to create a web page on the Authority's website and enter the project details for public view. The page must be updated quarterly with the number and types of apartments or plots booked, the garages booked, the approvals taken and pending, and the status of the project. Section 11(2) requires every advertisement or prospectus to mention the Authority's website address and the registration number.
Section 11(3) requires the promoter to make the sanctioned plans, layout plans and specifications available at the site, and to give the allottee the stage-wise time schedule for completion, including water, sanitation and electricity. Section 11(4) keeps the promoter responsible for the project until conveyance, including obtaining the completion or occupancy certificate and maintaining essential services until the association takes over.
Section 13(1) bars the promoter from accepting more than ten per cent of the cost of an apartment, plot or building as an advance or application fee without first entering into a written agreement for sale and registering it. Section 13(2) requires the agreement to state the payment schedule, the possession date and the interest rates for default by either side.
Section 14(1) requires the project to be developed in accordance with the sanctioned plans. Section 14(2) bars alterations to the apartment without the buyer's consent, and alterations to common areas or the building without the written consent of at least two-thirds of the allottees. Section 14(3) requires the promoter to rectify a structural or other defect brought to notice within five years of possession, without charge, within thirty days.
Extension, revocation and lapse
Section 6 allows the Authority to extend a registration on the promoter's application for force majeure, which the Explanation limits to war, flood, drought, fire, cyclone, earthquake or another natural calamity affecting the project. The Authority may also extend in reasonable circumstances without default by the promoter, for reasons recorded in writing, but the aggregate extension cannot exceed one year. An application for extension cannot be rejected without a hearing.
Section 7 allows the Authority to revoke a registration on a complaint, on its own motion or on the recommendation of the competent authority. The grounds are default in doing anything required by the Act, violation of the terms of the approval, unfair practice, or fraudulent practice. Section 7(2) requires at least thirty days' written notice stating the grounds, and consideration of the promoter's reply. Section 7(3) allows the Authority to impose conditions instead of revoking.
Section 8 deals with what happens after a registration lapses or is revoked. The Authority may consult the appropriate Government and arrange for the remaining development work to be carried out by the competent authority, by the association of allottees or in another manner. The association of allottees has the first right of refusal to carry out the remaining work after revocation. An order under Section 8 does not take effect until the appeal period has expired.
Penalties and checks before buying
Section 59(1) makes a promoter who contravenes Section 3 liable to a penalty of up to ten per cent of the estimated cost of the project, as determined by the Authority. Section 59(2) makes continued violation punishable with imprisonment of up to three years, a further fine of up to ten per cent of the estimated cost, or both.
A buyer can check the registration number on the TNRERA website before paying a booking amount. The project page should show the promoter's details, the sanctioned plans, the approvals, the declared completion date and the quarterly booking updates. A page that has not been updated for several quarters is a warning sign.
The agreement for sale should be registered, and the payment schedule should match the stage-wise completion schedule. A demand for more than ten per cent before the agreement is signed is a statutory violation. The buyer should also ask for the escrow account details and the chartered accountant's annual certificate, because those records show whether the collections are being used for the project.
Supreme Court decisions
Newtech Promoters and Developers Pvt. Ltd. v. State of Uttar Pradesh(2021) 18 SCC 1
The Act applies to ongoing projects; promoters of incomplete projects had to register and declare fresh timelines for the remaining work.
- Issue
- Whether the RERA Act applies to projects launched before it commenced, and whether promoters of incomplete projects had to register them.
- Held
- The Supreme Court upheld the application of the Act to ongoing projects. It described the Act as retroactive in operation and held that promoters of incomplete projects had to register and declare fresh timelines for the remaining development work. The argument that projects launched before 2016 fell outside the Act was rejected.
- In practice
- A promoter with an unfinished project must register it, declare a completion period that reflects the remaining work, and update the project page. A buyer can check the registration and revised timeline, and can use the declared completion date in any complaint about delay instead of the original brochure date.
Bikram Chatterji v. Union of India(2019) 9 SCC 161
When the promoter siphoned homebuyer money and left the Amrapali projects incomplete, the Supreme Court cancelled the group’s lease deeds, appointed NBCC to complete the projects, and directed an Enforcement Directorate investigation.
- Issue
- What the court would do with the project land, the homebuyers’ flats and the promoter’s liabilities after the Amrapali projects stalled.
- Held
- The Court cancelled the lease deeds granted to the Amrapali group by the Noida and Greater Noida Authorities and held that those authorities could not sell the homebuyers’ flats or the leased land to recover their own dues. It appointed NBCC to complete the projects, directed that homebuyers’ outstanding payments be deposited into an account with the Court and disbursed on completion, and, in view of the forensic auditors’ findings of FEMA violations and money laundering, directed the Enforcement Directorate and other authorities to investigate and fix liability.
- In practice
- A buyer facing a stalled project should ask for the forensic or audit report, the lease record and the status of the promoter’s attached properties. Press for completion by an independent agency and for protection of the flat from recovery of the promoter’s dues, and place any audit finding of diversion before the investigating agency as well as the consumer or RERA forum.
Questions
Which projects need RERA registration in Tamil Nadu?
A project in a planning area needs registration before any advertisement, booking or sale. Section 3(2)(a) exempts a project where the land does not exceed five hundred square metres or the number of apartments does not exceed eight, inclusive of all phases, and the State may reduce either threshold. Section 3(2)(b) exempts a project that had a completion certificate before the Act commenced. The Explanation to Section 3 treats every phase as a stand-alone project. Check the phase-wise registration numbers on the TNRERA project page before paying a booking amount.
Can a promoter advertise before registration?
No. Section 3(1) bars advertising, marketing, booking, selling or offering for sale without registration, and Section 11(2) requires every advertisement or prospectus to mention the Authority's website address and the registration number. The bar covers an invitation to purchase, not only a concluded sale, so a pre-launch page that invites bookings can fall within it. A buyer should ask for the registration number before responding to an advertisement and check it on the TNRERA website. A promoter should keep the advertisement copy and registration details on file.
What documents go with the application?
Section 4(2) lists the documents: the promoter's enterprise details, the projects launched in the past five years and their status, approvals and commencement certificate, sanctioned plan and layout, development plan and facilities, land location and boundaries, proforma allotment letter and agreement, carpet area and garage details, agent and contractor details, and an affidavit on title, encumbrances, completion period and the seventy per cent escrow. TNRERA's portal decides the upload format. Missing an approval or a stale project record is a common reason for a query, so reconcile the file against Section 4(2) before submission.
How long does registration take?
Section 5(1) gives the Authority thirty days to grant registration with a number, login id and password, or to reject the application for reasons recorded after a hearing. If neither happens, Section 5(2) deems the project registered and requires the number and login details within seven days after that period. The registration is valid for the completion period declared under Section 4(2)(l)(C). Deemed registration is a fallback, not a substitute for a complete application, so track the filing date and follow up in writing if the thirty days pass without a decision.
What is the seventy per cent escrow rule?
Section 4(2)(l)(D) requires the promoter to deposit seventy per cent of the amounts realised from allottees in a separate scheduled bank account and to use the money only for construction and land cost of that project. Withdrawals must match the percentage of completion and need a certificate from an engineer, an architect and a chartered accountant. The accounts must be audited within six months after the financial year and a certified utilisation statement produced. A buyer should ask for the escrow account details and the latest certificate before the next payment.
Can registration be extended?
Yes. Section 6 allows the Authority to extend registration on the promoter's application for force majeure, which the Explanation limits to war, flood, drought, fire, cyclone, earthquake or another natural calamity affecting the project. It may also extend in reasonable circumstances without default by the promoter, for reasons recorded in writing. The aggregate extension cannot exceed one year, and an application cannot be rejected without a hearing. A promoter should apply before the declared completion date and support the application with evidence of the event and the revised completion schedule.
What happens if a project is not registered?
Section 59(1) makes a promoter who contravenes Section 3 liable to a penalty of up to ten per cent of the estimated cost of the project, as the Authority determines. Section 59(2) makes a continued violation punishable with imprisonment of up to three years, a further fine of up to ten per cent of the estimated cost, or both. A buyer can complain to TNRERA about the unregistered project. Before paying, check the registration number on the project page and keep a screenshot of the advertisement.
This guide is general information on Indian real estate regulation as at 1 November 2026. It is not legal advice on any particular case.